MAS 2 coin automat for 2 – 8 showers

MAS 2.2 – MAS 2.8 are coin-operated controls intended for operating 2 to 8 end users (showers, washbasins, electric dryers, through-flow water heaters etc.).
The total time and charge for the use of the appliance can be set on the control. When setting up the control for the use with showers or washbasins that are equipped with the water meter it is also possible to set the amount of water expendable at one use. The user is given notice by interrupted water flow that the showering time is getting to its end.
The coin-operated automat should be supplemented with shower armatures SA 1.1 (SA 1.TV), SA 2.1 (SA 2.TV) or SA 11.1 produced by AZP Brno.
The power unit is not part of the delivery and must be resolved separately in the frame of the electro-installation project.
On order the coin-operated shower control can be equipped with a coin counter PM 1 or frame with lock cover.
The products are manufactured from the stainless steel AISI 304. Other materials (e.g. AISI 316) possible on order. For cleaning we recomnned WÜRTH detergents – material preservation (no. 0893 121 K) and material cleaning (no. 893 121 1).

Package contents

  • stainless steel casket
  • coin scanning device
  • electronics
  • box for coins
  • casket casing with a lock
  • combination box

PM 2 – coin counter
Frame with lock cover

Power supply 12V, 50Hz
Power requirement 8VA
Source of power supply ZAC MAS
Types of coins 1, 2, 5, 10, 20 CZK; 0,1; 0,2; 0,5; 1; 2 EUR and tokens ZT 2; other coins made to order
Time of showering 1 sec. - 5 hrs.
Time of stay in a cabin 1 sec. - 5 hrs.
Weight 3,6kg
  • Set up cable for power supply - 230 V, 50 Hz for source of power supply ZAC MAS
  • Set up alcoves for the control installation with combination box including installation pipe P29 (length max. 1,5m) to its connection
  • Set up alcove for SA 1 (SA 11) armature usage
  • Water and electricity distribution net is carried out as per schema

Example of connection to one water supply

Example of connection to one water supply

    • A
      cold water

n

    • B
      hot water

n

    • J
      connection box

n

    • K
      installation pipe P29

n

  • *
    not part of delivery

Example of connection to hot and cold water supply

Example of connection to hot and cold water supply

    • A
      cold water

n

    • B
      hot water

n

    • J
      connection box

n

    • K
      installation pipe P29

n

    • *
      not part of delivery

n

  • **
    Recommended temperature

Manual

Manual